Interconnection for Wind Energy; Notice Extending Compliance Date

---
identifier: "/us/fr/E5-6112"
source: "fr"
legal_status: "authoritative_unofficial"
title: "Interconnection for Wind Energy; Notice Extending Compliance Date"
title_number: 0
title_name: "Federal Register"
section_number: "E5-6112"
section_name: "Interconnection for Wind Energy; Notice Extending Compliance Date"
positive_law: false
currency: "2005-11-04"
last_updated: "2005-11-04"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "E5-6112"
document_type: "notice"
publication_date: "2005-11-04"
agencies:
  - "Energy Department"
  - "Federal Energy Regulatory Commission"
fr_citation: "70 FR 67156"
fr_volume: 70
docket_ids:
  - "Docket Nos. RM05-4-000 and RM05-4-001"
---

#  Interconnection for Wind Energy; Notice Extending Compliance Date

On June 2, 2005, the Commission issued its Final Rule in these proceedings. Interconnection for Wind Energy, Order No. 661, 70 FR 34993 (June 16, 2005), FERC Stats. & Regs. ¶ 31,186 (2005) (Final Rule). By order dated August 5, 2005, the Commission extended to November 14, 2005 the date by which public utilities that own, control, or operate transmission facilities in interstate commerce are to adopt the Final Rule Appendix G as amendments to the Large Generator Interconnection Procedures and Large Generator Interconnection Agreements in their Open Access Transmission Tariffs.

By this notice, the Commission hereby extends to December 30, 2005 the date by which public utilities that own, control, or operate transmission facilities in interstate commerce are to adopt the Final Rule Appendix G as amendments to the Large Generator Interconnection Procedures and Large Generator Interconnection Agreements in their Open Access Transmission Tariffs.

Magalie R. Salas,

Secretary.