Skip to content
LexBuild

PJM Interconnection, L.L.C.; Notice of Initiation of Proceeding and Refund Effective Date

---
identifier: "/us/fr/E6-7373"
source: "fr"
legal_status: "authoritative_unofficial"
title: "PJM Interconnection, L.L.C.; Notice of Initiation of Proceeding and Refund Effective Date"
title_number: 0
title_name: "Federal Register"
section_number: "E6-7373"
section_name: "PJM Interconnection, L.L.C.; Notice of Initiation of Proceeding and Refund Effective Date"
positive_law: false
currency: "2006-05-16"
last_updated: "2006-05-16"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "E6-7373"
document_type: "notice"
publication_date: "2006-05-16"
agencies:
  - "Energy Department"
  - "Federal Energy Regulatory Commission"
fr_citation: "71 FR 28315"
fr_volume: 71
docket_ids:
  - "Docket No. EL05-148-000"
  - "ER05-1410-000"
---

#  PJM Interconnection, L.L.C.; Notice of Initiation of Proceeding and Refund Effective Date

On April 20, 2006, the Commission issued an order that initiated a proceeding in Docket Nos. EL05-148-000 and ER05-1410-000, pursuant to section 206 of the Federal Power Act (FPS), 16 U.S.C. 824e (2005), concerning the justness and reasonableness of PJM Interconnection, L.L.C.'s reliability pricing model proposal (RPM). *PJM Interconnection, L.L.C.* , 115 FERC ¶ 61,079 (2006).

The refund effective date in Docket Nos. EL05-148-000 and ER05-1410-000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the *Federal Register* .

Magalie R. Salas,

Secretary.