# Carolina Power and Light Company; Errata Notice and Revised Schedule
On May 10, 2006 the Commission issued a “Notice of Application Tendered for Filing” regarding the above-referenced proceeding. This Errata makes the following correction to the notice:
(1) Under letter n., paragraph 4, the last sentence should be replaced by the following sentence: “During the 2002 drought, Progress Energy and APGI agreed, in a regional Emergency Drought Management Protocol (now expired), to operate the projects so as to achieve a daily average flow of 900 cfs at the Rockingham, North Carolina U.S. Geological Survey gage.”
(2) Under letter q. Procedural Schedule: The table is revised as follows:
| Milestone | Target date |
| --- | --- |
| Tendering Notice | May 10, 2006. |
| File Additional Study Requests | June 26, 2006. |
| Additional Information Requests (if necessary) | July 2006. |
| Issue Acceptance Letter and Solicit Interventions | October 2006. |
| Issue Scoping Document 1 for Comments | November 2006. |
| Hold Scoping Meetings | January 2006. |
| Request Additional Information (if necessary) | March 2007. |
| Issue Scoping Document 2 (if necessary) | March 2007. |
| Notice of Application Ready for Environmental Analysis | April 2007. |
| Filing of Recommendations, Preliminary Terms and Conditions, and Fishway Prescriptions | June 2007. |
| Notice of Availability of Draft EA or EIS | September 2007. |
| Comments on Draft EA or EIS and Modified Terms and Conditions | November 2007. |
| Notice of Availability of Final EA or EIS | March 2008. |
| Ready for Commission Decision on the Application | April 2008. |
Magalie R. Salas,
Secretary.