Skip to content
LexBuild

Electric Transmission Congestion Study

---
identifier: "/us/fr/E8-16222"
source: "fr"
legal_status: "authoritative_unofficial"
title: "Electric Transmission Congestion Study"
title_number: 0
title_name: "Federal Register"
section_number: "E8-16222"
section_name: "Electric Transmission Congestion Study"
positive_law: false
currency: "2008-07-16"
last_updated: "2008-07-16"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "E8-16222"
document_type: "notice"
publication_date: "2008-07-16"
agencies:
  - "Energy Department"
fr_citation: "73 FR 40859"
fr_volume: 73
fr_action: "Notice of date and time Changes for technical workshops."
---

#  Electric Transmission Congestion Study

**AGENCY:**

Office of Electricity Delivery and Energy Reliability, Department of Energy (DOE).

**ACTION:**

Notice of date and time Changes for technical workshops.

**SUMMARY:**

On June 4, 2008, DOE published a notice that DOE was initiating preparations for the 2009 National Electric Transmission Congestion Study pursuant to section 216(a)(1) of the Federal Power Act (73 FR 31846). In the June 4 notice, DOE stated that it would be hosting six regional technical workshops to receive and discuss input concerning electric transmission-level congestion. The date for the workshop in Atlanta and the starting time of the workshop in Chicago have been changed. The locations of the workshops remain the same.

**DATES:**

See *SUPPLEMENTARY INFORMATION* section for workshop date and time changes.

**FOR FURTHER INFORMATION CONTACT:**

David Meyer, DOE Office of Electricity Delivery and Energy Reliability, (202) 586-1411, *[email protected]* .

**SUPPLEMENTARY INFORMATION:**

**I. Date and Time Changes for Technical Workshops**

*Workshops dates and times:* The date for the Atlanta and the starting and ending time for the Chicago technical workshops are:

1. July 29, 2008, 9 a.m. to 12:30 p.m., Atlanta, GA.

2. September 17, 2008, 8:30 a.m. to 12 p.m., Chicago, IL.

Issued in Washington, DC on July 10, 2008.

Marshall E. Whitenton,

Deputy Assistant Secretary, Permitting, Siting and Analysis, Office of Electricity Delivery and Energy Reliability.