# Environmental Impact Statements; Notice of Availability
*Responsible Agency:* Office of Federal Activities, General Information (202) 564-7146 or *http://www.epa.gov/compliance/nepa/.*
Weekly receipt of Environmental Impact Statements.
Filed 06/09/2014 Through 06/13/2014.
Pursuant to 40 CFR 1506.9.
*Notice:* Section 309(a) of the Clean Air Act requires that EPA make public its comments on EISs issued by other Federal agencies. EPA's comment letters on EISs are available at: *http://www.epa.gov/compliance/nepa/eisdata.html.*
*EIS No. 20140171, Draft EIS,WAPA, NE,* Interconnection of the Grande Prairie Wind Farm, Comment Period Ends: 08/04/2014, Contact: Rod O'Sullivan 720-962-7260.
*EIS No. 20140172, Draft EIS, USACE, OR,* Double-crested Cormorant Management Plan to Reduce Predation of Juvenile Salmonids in the Columbia River Estuary, Comment Period Ends: 08/04/2014, Contact: Sondra Ruckwardt 503-808-4510.
*EIS No. 20140173, Final EIS, USFS, OR,* Wolf Fuels and Vegetation Management Project, Review Period Ends: 07/28/2014, Contact: Jeff Marszal 541-416-6436.
*EIS No. 20140174, Final EIS, USAF, NH,* Second Main Operating Base KC-46A Beddown at Alternative Air National Guard Installations, Review Period Ends: 07/21/2014, Contact: Kevin Marek 240-612-8855.
*EIS No. 20140175, Draft EIS, FERC, TX,* Corpus Christi LNG Project, Comment Period Ends: 08/04/2014, Contact: Kandi Barakat 202-502-6365.
*EIS No. 20140176, Final EIS, USACE, LA,* Calcasieu Lock, Louisiana Feasibility Study, Review Period Ends: 07/21/2014, Contact: Timothy K. George 314-331-8459.
*Amended Notice:*
*EIS No. 20140167, Final EIS, USACE, HI,* Honolulu Seawater Air Conditioning Project, Review Period Ends: 07/28/2014, Contact: Ryan Winn 808-835-4309.
Revision to the FR Notice Published 6/13/2014; Correct Review Period from 7/14/2014 to 07/28/214.
Dated: June 17, 2014.
Cliff Rader,
Director, NEPA Compliance Division, Office of Federal Activities.