Approval and Promulgation of Implementation Plans; Washington: Nonattainment New Source Review

---
identifier: "/us/fr/2014-26451"
source: "fr"
legal_status: "authoritative_unofficial"
title: "Approval and Promulgation of Implementation Plans; Washington: Nonattainment New Source Review"
title_number: 0
title_name: "Federal Register"
section_number: "2014-26451"
section_name: "Approval and Promulgation of Implementation Plans; Washington: Nonattainment New Source Review"
positive_law: false
currency: "2014-11-07"
last_updated: "2014-11-07"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Environmental Protection Agency"
document_number: "2014-26451"
document_type: "rule"
publication_date: "2014-11-07"
agencies:
  - "Environmental Protection Agency"
cfr_references:
  - "40 CFR Part 52"
fr_citation: "79 FR 66291"
fr_volume: 79
docket_ids:
  - "EPA-R10-OAR-2014-0343"
  - "FRL-9918-84-Region 10"
effective_date: "2014-12-08"
fr_action: "Final rule."
---

#  Identification of plan.

**AGENCY:**

Environmental Protection Agency.

**ACTION:**

Final rule.

**SUMMARY:**

The Environmental Protection Agency (EPA) is approving revisions to the Washington State Implementation Plan (SIP) that were submitted by the Department of Ecology (Ecology) on  January 27, 2014. These revisions update the preconstruction permitting regulations for large industrial (major source) facilities located in designated nonattainment areas, referred to as the Nonattainment New Source Review (major nonattainment NSR or major NNSR) program. While these revisions update Ecology's major NNSR program generally, the most significant change is the incorporation of regulations to implement major NNSR for fine particulate matter, particles with an aerodynamic diameter less than or equal to a nominal 2.5 micrometers (PM <sub>2.5</sub> ). The major NNSR program is designed to ensure that major stationary sources of air pollution are constructed or modified in a manner that is consistent with attainment and maintenance of the National Ambient Air Quality Standards (NAAQS).

**DATES:**

This final rule is effective on December 8, 2014.

**ADDRESSES:**

The EPA has established a docket for this action under Docket ID No. EPA-R10-OAR-2014-0343. All documents in the docket are listed on the *www.regulations.gov* Web site. Although listed in the index, some information is not publicly available, e.g., Confidential Business Information (CBI) or other information the disclosure of which is restricted by statute. Certain other material, such as copyrighted material, is not placed on the Internet and will be publicly available only in hard copy form. Publicly available docket materials are available either electronically through *www.regulations.gov* or in hard copy at the Air Programs Unit, Office of Air Waste and Toxics, EPA Region 10, 1200 Sixth Avenue, Seattle, WA, 98101. The EPA requests that if at all possible, you contact the individual listed in the *FOR FURTHER INFORMATION CONTACT* section to view the hard copy of the docket. You may view the hard copy of the docket Monday through Friday, 8:00 a.m. to 4:00 p.m., excluding Federal holidays.

**FOR FURTHER INFORMATION CONTACT:**

Jeff Hunt at (206) 553-0256, *[email protected],* or by using the above EPA, Region 10 address.

**SUPPLEMENTARY INFORMATION:**

**Definitions**

For the purpose of this document, we are giving meaning to certain words or initials as follows:

(i) The words or initials “Act” or “CAA” mean or refer to the Clean Air Act, unless the context indicates otherwise.

(ii) The words “EPA”, “we”, “us” or “our” mean or refer to the Environmental Protection Agency.

(iii) The initials “SIP” mean or refer to State Implementation Plan.

(iv) The words “Washington” and “State” mean the State of Washington.

**Table of Contents**

I. Background Information

II. Final Action

III. Statutory and Executive Orders Review

**I. Background Information**

On January 27, 2014, Washington submitted revisions updating the general air quality regulations that apply to sources within Ecology's jurisdiction, including the major nonattainment NSR permitting program. On July 25, 2014, the EPA proposed to approve the major nonattainment NSR-related provisions contained in the submittal (79 FR 43345). An explanation of the CAA requirements, a detailed explanation of the revisions, and the EPA's reasons for approval were provided in the notice of proposed rulemaking, and will not be restated here. The public comment period for this proposed rule ended on August 25, 2014. We did not receive any comments on the proposal.

**II. Final Action**

The EPA is approving the major nonattainment NSR-related provisions listed in the table below. As discussed in the proposed rulemaking, the EPA intends to take action on the remaining provisions included in Ecology's January 27, 2014 submittal, related to the Prevention of Significant Deterioration and visibility permitting requirements for major stationary sources, in a separate, future action. The EPA is also approving the general air quality regulations contained in Washington Administrative Code (WAC) 173-400-110 through-112 and WAC 173-400-171, which were previously approved by the EPA for purposes of minor new source review, as consistent with the EPA's requirements for major nonattainment NSR. For more information see 79 FR 59653, October 3, 2014.

At this time, the EPA's approval of the major nonattainment NSR-related provisions listed in the table below is limited to only those counties or sources where Ecology has direct jurisdiction. This approval excludes sources subject to Energy Facility Site Evaluation Council (EFSEC) or local clean air agency jurisdiction, as described in the proposed rulemaking. The counties where Ecology has direct jurisdiction are: Adams, Asotin, Chelan, Columbia, Douglas, Ferry, Franklin, Garfield, Grant, Kittitas, Klickitat, Lincoln, Okanogan, Pend Oreille, San Juan, Stevens, Walla Walla, and Whitman. The EPA also notes that under the SIP-approved provisions of WAC 173-405-012, WAC 173-410-012, and WAC 173-415-012, Ecology has statewide, direct jurisdiction for kraft pulping mills, sulfite pulping mills, and primary aluminum plants, including the RockTenn facility located in the Tacoma-Pierce County fine particulate matter nonattainment area.

| State citation | Title/subject | State | Explanation |
| --- | --- | --- | --- |
|  |  |  |  |
| 173-400-131 | Issuance of Emission Reduction Credits | 4/1/11 |  |
| 173-400-136 | Use of Emission Reduction Credits (ERC) | 12/29/12 |  |
| 173-400-800 | Major Stationary Source and Major Modification in a Nonattainment Area | 4/1/11 |  |
| 173-400-810 | Major Stationary Source and Major Modification Definitions | 12/29/12 |  |
| 173-400-820 | Determining if a New Stationary Source or Modification to a Stationary Source is Subject to these Requirements | 12/29/12 |  |
| 173-400-830 | Permitting Requirements | 12/29/12 |  |
| 173-400-840 | Emission Offset Requirements | 12/29/12 |  |
| 173-400-850 | Actual Emissions Plantwide Applicability Limitation (PAL) | 12/29/12 |  |
| 173-400-860 | Public Involvement Procedures | 4/1/11 |  |

**III. Statutory and Executive Orders Review**

Under the CAA, the Administrator is required to approve a SIP submission that complies with the provisions of the Act and applicable Federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in reviewing SIP submissions, the EPA's role is to approve State choices, provided that they meet the criteria of the Clean Air Act. Accordingly, this action merely approves State law as meeting Federal requirements and does not impose additional requirements beyond those imposed by State law. For that reason, this action:

• Is not a “significant regulatory action” subject to review by the Office of Management and Budget under Executive Order 12866 (58 FR 51735, October 4, 1993);

• does not impose an information collection burden under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 *et seq.* );

• is certified as not having a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 *et seq.* );

• does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4);

• does not have Federalism implications as specified in Executive Order 13132 (64 FR 43255, August 10, 1999);

• is not an economically significant regulatory action based on health or safety risks subject to Executive Order 13045 (62 FR 19885, April 23, 1997);

• is not a significant regulatory action subject to Executive Order 13211 (66 FR 28355, May 22, 2001);

• is not subject to requirements of Section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because this action does not involve technical standards; and

• does not provide the EPA with the discretionary authority to address, as appropriate, disproportionate human health or environmental effects, using practicable and legally permissible methods, under Executive Order 12898 (59 FR 7629, February 16, 1994).

The SIP is not approved to apply on any Indian reservation land in Washington except for as specifically noted below and is also not approved to apply in any other area where the EPA or an Indian tribe has demonstrated that a tribe has jurisdiction. In those areas of Indian country, the rule does not have tribal implications as specified by Executive Order 13175 (65 FR 67249, November 9, 2000), nor will it impose substantial direct costs on tribal governments or preempt tribal law. Washington's SIP is approved to apply on non-trust land within the exterior boundaries of the Puyallup Indian Reservation, also known as the 1873 Survey Area. Under the *Puyallup Tribe of Indians Settlement Act of 1989,* 25 U.S.C. 1773, Congress explicitly provided state and local agencies in Washington authority over activities on non-trust lands within the 1873 Survey Area. Consistent with EPA policy, the EPA nonetheless provided a consultation opportunity to the Puyallup Tribe in a letter dated February 25, 2014. The EPA did not receive a request for consultation.

The Congressional Review Act, 5 U.S.C. 801 *et seq.,* as added by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. The EPA will submit a report containing this action and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States prior to publication of the rule in the *Federal Register* . A major rule cannot take effect until 60 days after it is published in the *Federal Register* . This action is not a “major rule” as defined by 5 U.S.C. 804(2).

Under section 307(b)(1) of the Clean Air Act, petitions for judicial review of this action must be filed in the United States Court of Appeals for the appropriate circuit by January 6, 2015. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this action for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements. (See section 307(b)(2).)

**List of Subjects in 40 CFR Part 52**

Environmental protection, Air pollution control, Carbon monoxide, Incorporation by reference, Intergovernmental relations, Lead, Nitrogen dioxide, Ozone, Particulate matter, Reporting and recordkeeping requirements, Sulfur oxides, Volatile organic compounds.

Dated: October 22, 2014.

Dennis J. McLerran,

Regional Administrator, Region 10.

For the reasons stated in the preamble, 40 CFR part 52 is amended as follows:

**40 CFR Part 52**

**PART 52—APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS**

1. The authority citation for part 52 continues to read as follows:

**Authority:**

42 U.S.C. 7401 et seq.

**40 CFR Part 52**

**Subpart WW—Washington**

2. Section 52.2470 is amended in paragraph (c), table 2, by:

a. Adding in numerical order entries for 173-400-131, 173-400-136, and 173-400-800 through 173-400-860.

b. Revising the footnote at the bottom of the table.

The additions and revisions read as follows:

§ 52.2470

(c) * * *

| State citation | Title/Subject | State | EPA Approval date | Explanations |
| --- | --- | --- | --- | --- |
|  |  |  |  |  |
|  |  |  |  |  |
| *         *         *         *         *         *         * |  |  |  |  |
| 173-400-131 | Issuance of Emission Reduction Credits | 4/1/11 | 11/7/14[Insert 
                                    
                                     citation] |  |
| 173-400-136 | Use of Emission Reduction Credits (ERC) | 12/29/12 | 11/7/14[Insert 
                                    
                                     citation] |  |
|  |  |  |  |  |
| *         *         *         *         *         *         * |  |  |  |  |
| 173-400-800 | Major Stationary Source and Major Modification in a Nonattainment Area | 4/1/11 | 11/7/14[Insert 
                                    
                                     citation] |  |
| 173-400-810 | Major Stationary Source and Major Modification Definitions | 12/29/12 | 11/7/14[Insert 
                                    
                                     citation] |  |
| 173-400-820 | Determining if a New Stationary Source or Modification to a Stationary Source is Subject to these Requirements | 12/29/12 | 11/7/14[Insert 
                                    
                                     citation] |  |
| 173-400-830 | Permitting Requirements | 12/29/12 | 11/7/14[Insert 
                                    
                                     citation] |  |
| 173-400-840 | Emission Offset Requirements | 12/29/12 | 11/7/14[Insert 
                                    
                                     citation] |  |
| 173-400-850 | Actual Emissions Plantwide Applicability Limitation (PAL) | 12/29/12 | 11/7/14[Insert 
                                    
                                     citation] |  |
| 173-400-860 | Public Involvement Procedures | 4/1/11 | 11/7/14[Insert 
                                    