Skip to content
LexBuild

Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations

---
identifier: "/us/fr/2015-20538"
source: "fr"
legal_status: "authoritative_unofficial"
title: "Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations"
title_number: 0
title_name: "Federal Register"
section_number: "2015-20538"
section_name: "Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations"
positive_law: false
currency: "2015-08-20"
last_updated: "2015-08-20"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "2015-20538"
document_type: "rule"
publication_date: "2015-08-20"
agencies:
  - "Energy Department"
  - "Federal Energy Regulatory Commission"
cfr_references:
  - "18 CFR Part 2"
  - "18 CFR Part 157"
fr_citation: "80 FR 50558"
fr_volume: 80
docket_ids:
  - "Docket No. RM12-11-003"
  - "Order No. 790-B"
effective_date: "2015-10-07"
fr_action: "Final rule, order on clarification; correction."
---

#  Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations

**AGENCY:**

Federal Energy Regulatory Commission.

**ACTION:**

Final rule, order on clarification; correction.

**SUMMARY:**

This document contains corrections to the final rule (RM12-11-003) which was published in the *Federal Register* of Friday, July 24, 2015 (80 FR 43944). The final rule amended regulations to: provide pre-granted authority under a new paragraph to abandon or replace auxiliary facilities, subject to certain conditions; permit auxiliary facilities that cannot meet the conditions for the pre-granted abandonment authority in the new paragraph to be abandoned under the blanket certificate regulations, subject to those regulations' requirements; and permit replacement facilities constructed under the regulations to be abandoned under the blanket certificate regulations, subject to those regulations' requirements.

**DATES:**

Effective October 7, 2015.

**FOR FURTHER INFORMATION CONTACT:**

Katherine Liberty, Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, (202) 502-6491, *[email protected]* .

Gordon Wagner, Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, (202) 502-8947, *[email protected]* .

Howard Wheeler, Office of Energy Projects, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, (202) 502-8688, *[email protected]* .

Shannon Jones, Office of Energy Projects, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, (202) 502-6410, *[email protected]* .

**SUPPLEMENTARY INFORMATION:**

**Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations Docket No. RM12-11-003**

**Errata Notice**

On July 16, 2015, the Commission issued a Final Rule in the above  captioned proceeding. *Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations,* 152 FERC ¶ 61,049 (2015). This errata notice makes a correction to the Final Rule as issued.

In FR Doc. 2015-17919 appearing on page 43949 in the *Federal Register* of Friday, July 24, 2015, the following correction is made:

1. On page 43949, in the second column, § 157.216(b)(2)(i)(A) of the regulatory text is revised to read as follows:

“(A) Will not exceed the cost limit in § 157.208(d) for activities under the prior notice provisions;”

Dated: August 14, 2015.

Kimberly D. Bose,

Secretary.