# Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations
**AGENCY:**
Federal Energy Regulatory Commission.
**ACTION:**
Final rule, order on clarification; correction.
**SUMMARY:**
This document contains corrections to the final rule (RM12-11-003) which was published in the *Federal Register* of Friday, July 24, 2015 (80 FR 43944). The final rule amended regulations to: provide pre-granted authority under a new paragraph to abandon or replace auxiliary facilities, subject to certain conditions; permit auxiliary facilities that cannot meet the conditions for the pre-granted abandonment authority in the new paragraph to be abandoned under the blanket certificate regulations, subject to those regulations' requirements; and permit replacement facilities constructed under the regulations to be abandoned under the blanket certificate regulations, subject to those regulations' requirements.
**DATES:**
Effective October 7, 2015.
**FOR FURTHER INFORMATION CONTACT:**
Katherine Liberty, Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, (202) 502-6491, *[email protected]* .
Gordon Wagner, Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, (202) 502-8947, *[email protected]* .
Howard Wheeler, Office of Energy Projects, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, (202) 502-8688, *[email protected]* .
Shannon Jones, Office of Energy Projects, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, (202) 502-6410, *[email protected]* .
**SUPPLEMENTARY INFORMATION:**
**Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations Docket No. RM12-11-003**
**Errata Notice**
On July 16, 2015, the Commission issued a Final Rule in the above captioned proceeding. *Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations,* 152 FERC ¶ 61,049 (2015). This errata notice makes a correction to the Final Rule as issued.
In FR Doc. 2015-17919 appearing on page 43949 in the *Federal Register* of Friday, July 24, 2015, the following correction is made:
1. On page 43949, in the second column, § 157.216(b)(2)(i)(A) of the regulatory text is revised to read as follows:
“(A) Will not exceed the cost limit in § 157.208(d) for activities under the prior notice provisions;”
Dated: August 14, 2015.
Kimberly D. Bose,
Secretary.