Skip to content
LexBuild

C.P. Crane LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date

---
identifier: "/us/fr/2015-33124"
source: "fr"
legal_status: "authoritative_unofficial"
title: "C.P. Crane LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date"
title_number: 0
title_name: "Federal Register"
section_number: "2015-33124"
section_name: "C.P. Crane LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date"
positive_law: false
currency: "2016-01-05"
last_updated: "2016-01-05"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "2015-33124"
document_type: "notice"
publication_date: "2016-01-05"
agencies:
  - "Energy Department"
  - "Federal Energy Regulatory Commission"
fr_citation: "81 FR 231"
fr_volume: 81
docket_ids:
  - "Docket No. EL16-21-000"
---

#  C.P. Crane LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date

On December 29, 2015, the Commission issued an order in Docket No. EL16-21-000, pursuant to section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e (2012), instituting an investigation into the justness and reasonableness of C.P. Crane LLC's reactive power rate schedule. *C.P. Crane LLC* , 153 FERC ¶ 61,348 (2015).

The refund effective date in Docket No. EL16-21-000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the *Federal Register* .

Dated: December 29, 2015.

Nathaniel J. Davis, Sr.,

Deputy Secretary.