Columbia Gas Transmission, LLC; Notice of Revised Schedule for Environmental Review of the B-System Project

---
identifier: "/us/fr/2017-03565"
source: "fr"
legal_status: "authoritative_unofficial"
title: "Columbia Gas Transmission, LLC; Notice of Revised Schedule for Environmental Review of the B-System Project"
title_number: 0
title_name: "Federal Register"
section_number: "2017-03565"
section_name: "Columbia Gas Transmission, LLC; Notice of Revised Schedule for Environmental Review of the B-System Project"
positive_law: false
currency: "2017-02-24"
last_updated: "2017-02-24"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "2017-03565"
document_type: "notice"
publication_date: "2017-02-24"
agencies:
  - "Energy Department"
  - "Federal Energy Regulatory Commission"
fr_citation: "82 FR 11568"
fr_volume: 82
docket_ids:
  - "Docket Nos. CP16-498-000"
  - "PF16-4-000"
---

#  Columbia Gas Transmission, LLC; Notice of Revised Schedule for Environmental Review of the B-System Project

This notice identifies the Federal Energy Regulatory Commission staff's revised schedule for the completion of the environmental assessment (EA) for Columbia Gas Transmission, LLC's (Columbia) B-System Project. The original notice of schedule, issued on December 20, 2016, identified March 13, 2017 as the EA issuance date. Due to updated B-System Project information filed by Columbia on February 7, 2017, staff has revised the schedule for issuance of the EA.

**Schedule for Environmental Review**

Issuance of EA—April 28, 2017

90-day Federal Authorization Decision Deadline—July 27, 2017

If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project's progress.

**Additional Information**

In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription ( *http://www.ferc.gov/docs-filing/esubscription.asp* ). Additional information about the project may be obtained by contacting the Environmental Project Manager, Kenneth Warn, by telephone at 202-502-6859 or by electronic mail at *[email protected].*

Dated: February 16, 2017.

Nathaniel J. Davis, Sr.,

Deputy Secretary.