# Columbia Gas Transmission, LLC; Notice of Revised Schedule for Environmental Review of the B-System Project
This notice identifies the Federal Energy Regulatory Commission staff's revised schedule for the completion of the environmental assessment (EA) for Columbia Gas Transmission, LLC's (Columbia) B-System Project. The original notice of schedule, issued on December 20, 2016, identified March 13, 2017 as the EA issuance date. Due to updated B-System Project information filed by Columbia on February 7, 2017, staff has revised the schedule for issuance of the EA.
**Schedule for Environmental Review**
Issuance of EA—April 28, 2017
90-day Federal Authorization Decision Deadline—July 27, 2017
If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project's progress.
**Additional Information**
In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription ( *http://www.ferc.gov/docs-filing/esubscription.asp* ). Additional information about the project may be obtained by contacting the Environmental Project Manager, Kenneth Warn, by telephone at 202-502-6859 or by electronic mail at *[email protected].*
Dated: February 16, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.