# Green Mountain Power Corporation, Hydro Power, LLC; Notice of Transfer of Exemption
1. On February 1, 2021, Green Mountain Power Corporation, exemptee for the Woodsville Hydroelectric Project No. 5307, filed a letter notifying the Commission that the project was transferred from Green Mountain Power Corporation to Hydro Power, LLC. The exemption from licensing was originally issued on February 5, 1982. [^1] The project is located on the Ammonoosuc River, Grafton County, New Hampshire. The transfer of an exemption does not require Commission approval.
[^1]*New England Hydro, Inc., and Woodsville Fire District,* 18 FERC 62,158 (1982). On June 27, 2017, the project was transferred to *Green Mountain Power Corporation.*
2. Hydro Power, LLC is now the exemptee of the Woodsville Hydroelectric Project No. 5307. All correspondence must be forwarded to: Mr. Brandon L. Boudreau, 87 Factory Street, St. Johnsbury, VT 05819, Email: *[email protected].*
Dated: February 24, 2021.
Kimberly D. Bose,
Secretary.