Skip to content
LexBuild

Alice Falls Hydro, LLC; Notice of Intent To Prepare an Environmental Assessment

---
identifier: "/us/fr/2023-09027"
source: "fr"
legal_status: "authoritative_unofficial"
title: "Alice Falls Hydro, LLC; Notice of Intent To Prepare an Environmental Assessment"
title_number: 0
title_name: "Federal Register"
section_number: "2023-09027"
section_name: "Alice Falls Hydro, LLC; Notice of Intent To Prepare an Environmental Assessment"
positive_law: false
currency: "2023-04-28"
last_updated: "2023-04-28"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "2023-09027"
document_type: "notice"
publication_date: "2023-04-28"
agencies:
  - "Energy Department"
  - "Federal Energy Regulatory Commission"
fr_citation: "88 FR 26298"
fr_volume: 88
docket_ids:
  - "Project No. 5867-054"
---

#  Alice Falls Hydro, LLC; Notice of Intent To Prepare an Environmental Assessment

On September 29, 2021, Alice Falls Hydro, LLC filed an application for a new major license for the 2.1-megawatt Alice Falls Hydroelectric Project (Alice Falls Project or project; FERC No. 5867). The Alice Falls Project is located on the Ausable River, in the Town of Chesterfield, Clinton and Essex counties, New York.

In accordance with the Commission's regulations, on February 16, 2023, Commission staff issued a notice that the project was ready for environmental analysis (REA notice). Based on the information in the record, including comments filed on the REA notice, staff does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to license the Alice Falls Project.

The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission's final licensing decision.

The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate.

| Milestone | Target date |
| --- | --- |
| Commission issues EA | December 2023. |
| Comments on EA | January 2024. |

Any questions regarding this notice may be directed to Nicholas Tackett at (202) 502-6783 or *[email protected].*

Dated: April 24, 2023.

Kimberly D. Bose,

Secretary.