Skip to content
LexBuild

Northern States Power Company-Wisconsin; Notice of Intent To Prepare an Environmental Assessment

---
identifier: "/us/fr/2023-25398"
source: "fr"
legal_status: "authoritative_unofficial"
title: "Northern States Power Company-Wisconsin; Notice of Intent To Prepare an Environmental Assessment"
title_number: 0
title_name: "Federal Register"
section_number: "2023-25398"
section_name: "Northern States Power Company-Wisconsin; Notice of Intent To Prepare an Environmental Assessment"
positive_law: false
currency: "2023-11-17"
last_updated: "2023-11-17"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "2023-25398"
document_type: "notice"
publication_date: "2023-11-17"
agencies:
  - "Energy Department"
  - "Federal Energy Regulatory Commission"
fr_citation: "88 FR 80291"
fr_volume: 88
docket_ids:
  - "Project No. 2639-028"
---

#  Northern States Power Company-Wisconsin; Notice of Intent To Prepare an Environmental Assessment

On November 30, 2021, Northern States Power Company-Wisconsin filed an application for a new major license to continue operating the existing, licensed, 30.75-megawatt Cornell Hydroelectric Project No. 2639 (Cornell Project). The project is located on the Lower Chippewa River, in the township of Cornell, in Chippewa County, Wisconsin. The project does not occupy Federal land.

In accordance with the Commission's regulations, on July 14, 2023, Commission staff issued a notice that the project was ready for environmental analysis (REA notice). Based on the information in the record staff does not anticipate that licensing the project would constitute a major Federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to license the Cornell Project.

The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission's final licensing decision.

The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate.

| Milestone | Target date |
| --- | --- |
| Commission issues EA | April 2024 |
| Comments on EA | May 2024. |

Any questions regarding this notice may be directed to Michael Davis at *[email protected]* or call at 202-502-8339.

Dated: November 9, 2023.

Kimberly D. Bose,

Secretary.