# Environmental Impact Statements; Notice of Availability
*Responsible Agency:* Office of Federal Activities, General Information 202-564-5632 or *https://www.epa.gov/nepa.*
Weekly receipt of Environmental Impact Statements (EIS)
Filed February 12, 2024 10 a.m. EST Through February 16, 2024 10 a.m. EST
Pursuant to 40 CFR 1506.9.
**Notice**
Section 309(a) of the Clean Air Act requires that EPA make public its comments on EISs issued by other Federal agencies. EPA's comment letters on EISs are available at: *https://cdxapps.epa.gov/cdx-enepa-II/public/action/eis/search.*
*EIS No. 20240029, Draft, GSA, AK,* Alcan Land Port of Entry Expansion and Modernization Draft Environmental Impact Statement Alcan, Alaska, Comment Period Ends: 04/11/2024, Contact: Aaron Evanson 206-445-5876.
*EIS No. 20240030, Final, NRCS, PRO,* ADOPTION—PROGRAMMATIC—Habitat Restoration Activities Implemented throughout the Coastal United States, Review Period Ends: 03/25/2024, Contact: Angela Trahan 337-291-3142.
The Natural Resource Conservation Service (NRCS) has adopted the National Oceanic and Atmospheric Administration's Final EIS No. 20150171 filed 06/11/2015 with the Environmental Protection Agency. The NRCS was not a cooperating agency on this project. Therefore, republication of the document is necessary under Section 1506.3(b)(1) of the CEQ regulations.
*EIS No. 20240031, Final, TVA, TN,* Kingston Fossil Plant Retirement, Review Period Ends: 03/25/2024, Contact: Chevales Williams 423-751-7316.
Dated: February 20, 2024.
Julie Smith,
Acting Director, NEPA Compliance Division, Office of Federal Activities.