# South Sutter Water District; Notice of Revised Procedural Schedule for Environmental Assessment for the Proposed Project Relicense
On December 28, 2023, the South Sutter Water District (SSWD) filed an application for a new license to continue to operate and maintain the 6.8-megawatt Camp Far West Hydroelectric Project No. 2997 (Camp Far West Project). On November 25, 2024, Commission staff issued a notice of intent to prepare an environmental assessment (EA) to evaluate the effects of relicensing the Camp Far West Project. The notice included an anticipated schedule for issuing the EA in November 2025.
Staff are still evaluating the effects of relicensing the Camp Far West Project. In order for staff to fully consider all the information filed by SSWD, the procedural schedule for completing the EA is being revised as follows. Further revisions to the schedule may be made as appropriate.
| Milestone | Target date |
| --- | --- |
| Commission issues EA | February 27, 2026. |
| Commission on the EA | March 29, 2026. |
Questions regarding this notice may be directed to Quinn Emmering at (202) 502-6382 or *[email protected].*
Dated: November 20, 2025.
Debbie-Anne A. Reese,