# Minor Modification Approval
**AGENCY:**
Susquehanna River Basin Commission.
**ACTION:**
Notice.
**SUMMARY:**
This notice lists the minor modifications approved for previously approved projects by the Susquehanna River Basin Commission during the period set forth in *DATES* .
**DATES:**
January 1-31, 2026.
**ADDRESSES:**
Susquehanna River Basin Commission, 4423 North Front Street, Harrisburg, PA 17110-1788.
**FOR FURTHER INFORMATION CONTACT:**
Jason E. Oyler, General Counsel and Secretary to the Commission, telephone: (717) 238-0423, ext. 1312; fax (717) 238-2436; email: *[email protected].* Regular mail inquiries may be sent to the above address.
**SUPPLEMENTARY INFORMATION:**
This notice lists previously approved projects, receiving approval of minor modification or a corrective modification, described below, pursuant to 18 CFR 806.18 or to Commission Resolution Nos. 2013-11 and 2015-06, for the time period specified above.
1. Repsol Oil & Gas USA, LLC—Seeley Creek, Docket No. 20251216, Wells Township, Bradford County, Pa.; modification approval to change the passby monitoring location; Approval Date: January 8, 2026.
2. Amazon Data Services, Inc.—PHL100 Data Center, Docket No. 20251217, Salem Township, Luzerne County, Pa.; modification approval to add sources of water for consumptive use; Approval Date: January 26, 2026.
(Authority: Public Law 91-575, 84 Stat. 1509 *et seq.,* 18 CFR parts 806 and 808.)
Dated: January 27, 2026.
Jason E. Oyler,
General Counsel and Secretary to the Commission.