# § 1134. Acquisition, production, deployment, and support
**(a)** **In General.—** The Commandant shall—
**(1)** ensure there is a stable and efficient production and support capability to develop an asset or capability for the Coast Guard;
**(2)** conduct follow-on testing to confirm and monitor performance and correct deficiencies; and
**(3)** conduct acceptance tests and trials prior to the delivery of each asset or system to ensure the delivered asset or system achieves full operational capability.
**(b)** **Elements.—** The Commandant shall—
**(1)** execute production contracts;
**(2)** ensure that delivered assets and capabilities meet operational cost and schedules requirements established in the acquisition program baseline;
**(3)** validate manpower and training requirements to meet system needs to operate, maintain, support, and instruct the assets or capabilities; and
**(4)** prepare an acquisition project or program transition plan to enter into programmatic sustainment, operations, and support.
---
**Source Credit**: (Added Pub. L. 111–281, title IV, § 402(a), Oct. 15, 2010, 124 Stat. 2947, § 574; renumbered § 1134, Pub. L. 115–282, title I, § 108(b), Dec. 4, 2018, 132 Stat. 4208.)
## Editorial Notes
### Amendments
2018— renumbered as this section.