49 USC § 22903 - Project management oversight

---
identifier: "/us/usc/t49/s22903"
source: "usc"
legal_status: "official_legal_evidence"
title: "49 USC § 22903 - Project management oversight"
title_number: 49
title_name: "TRANSPORTATION"
section_number: "22903"
section_name: "Project management oversight"
chapter_number: 229
chapter_name: "RAIL IMPROVEMENT GRANTS"
part_number: "B"
part_name: "ASSISTANCE"
positive_law: true
currency: "119-84"
last_updated: "2026-04-17"
format_version: "1.1.0"
generator: "[email protected]"
source_credit: "(Added Pub. L. 110–432, div. B, title III, § 301(a), Oct. 16, 2008, 122 Stat. 4941, § 24403; amended Pub. L. 114–94, div. A, title XI, § 11316(p), Dec. 4, 2015, 129 Stat. 1679; renumbered § 22903, Pub. L. 115–420, § 7(a)(1), Jan. 3, 2019, 132 Stat. 5445.)"
---

# § 22903. Project management oversight

**(a)** **Project Management Plan Requirements.—** To receive Federal financial assistance for a major capital project under this chapter, an applicant must prepare and carry out a project management plan approved by the Secretary of Transportation. The plan shall provide for—

**(1)** adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;

**(2)** a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;

**(3)** a construction schedule for the project;

**(4)** a document control procedure and recordkeeping system;

**(5)** a change order procedure that includes a documented, systematic approach to handling the construction change orders;

**(6)** organizational structures, management skills, and staffing levels required throughout the construction phase;

**(7)** quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;

**(8)** material testing policies and procedures;

**(9)** internal plan implementation and reporting requirements;

**(10)** criteria and procedures to be used for testing the operational system or its major components;

**(11)** periodic updates of the plan, especially related to project budget and project schedule, financing, and ridership estimates; and

**(12)** the recipient’s commitment to submit periodically a project budget and project schedule to the Secretary.

**[(b)** Repealed. Pub. L. 114–94, div. A, title XI, § 11316(p), Dec. 4, 2015, 129 Stat. 1679]

**(c)** **Access to Sites and Records.—** Each recipient of assistance under this chapter shall provide the Secretary and a contractor the Secretary chooses under subsection (b) of this section with access to the construction sites and records of the recipient when reasonably necessary.

---

**Source Credit**: (Added Pub. L. 110–432, div. B, title III, § 301(a), Oct. 16, 2008, 122 Stat. 4941, § 24403; amended Pub. L. 114–94, div. A, title XI, § 11316(p), Dec. 4, 2015, 129 Stat. 1679; renumbered § 22903, Pub. L. 115–420, § 7(a)(1), Jan. 3, 2019, 132 Stat. 5445.)

## Editorial Notes

### Amendments

2019— renumbered  as this section.

2015—Subsec. (b).  struck out subsec. (b) which related to secretarial oversight.