Skip to content
LexBuild

30 CFR § 250.1729 - After I remove a platform or other facility, what information must I submit?

---
identifier: "/us/cfr/t30/s250.1729"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "30 CFR § 250.1729 - After I remove a platform or other facility, what information must I submit?"
title_number: 30
title_name: "Mineral Resources"
section_number: "250.1729"
section_name: "After I remove a platform or other facility, what information must I submit?"
chapter_name: "BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "B"
subchapter_name: "OFFSHORE"
part_number: "250"
part_name: "OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334."
regulatory_source: "76 FR 64462, Oct. 18, 2011, unless otherwise noted."
cfr_part: "250"
---

# 250.1729 After I remove a platform or other facility, what information must I submit?

Within 30 days after you remove a platform or other facility, you must submit a written report to the Regional Supervisor that includes the following:

(a) A summary of the removal operation including the date it was completed;

(b) A description of any mitigation measures you took; and

(c) A statement signed by your authorized representative that certifies that the types and amount of explosives you used in removing the platform or other facility were consistent with those set forth in the approved removal application.