Skip to content
LexBuild

30 CFR § 250.1730 - When might BSEE approve partial structure removal or toppling in place?

---
identifier: "/us/cfr/t30/s250.1730"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "30 CFR § 250.1730 - When might BSEE approve partial structure removal or toppling in place?"
title_number: 30
title_name: "Mineral Resources"
section_number: "250.1730"
section_name: "When might BSEE approve partial structure removal or toppling in place?"
chapter_name: "BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "B"
subchapter_name: "OFFSHORE"
part_number: "250"
part_name: "OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334."
regulatory_source: "76 FR 64462, Oct. 18, 2011, unless otherwise noted."
cfr_part: "250"
---

# 250.1730 When might BSEE approve partial structure removal or toppling in place?

The Regional Supervisor may grant a departure from the requirement to remove a platform or other facility by approving partial structure removal or toppling in place for conversion to an artificial reef if you meet the following conditions:

(a) The structure becomes part of a State artificial reef program, and the responsible State agency acquires a permit from the U.S. Army Corps of Engineers and accepts title and liability for the structure; and

(b) You satisfy any U.S. Coast Guard (USCG) navigational requirements for the structure.