Skip to content
LexBuild

30 CFR § 250.245 - May I combine the Project Conceptual Plan and the DWOP?

---
identifier: "/us/cfr/t30/s250.245"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "30 CFR § 250.245 - May I combine the Project Conceptual Plan and the DWOP?"
title_number: 30
title_name: "Mineral Resources"
section_number: "250.245"
section_name: "May I combine the Project Conceptual Plan and the DWOP?"
chapter_name: "BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "B"
subchapter_name: "OFFSHORE"
part_number: "250"
part_name: "OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334."
regulatory_source: "76 FR 64462, Oct. 18, 2011, unless otherwise noted."
cfr_part: "250"
---

# 250.245 May I combine the Project Conceptual Plan and the DWOP?

If your development project meets the following criteria, you may submit a combined Project Conceptual Plan/DWOP that complies with all applicable requirements for both, on or before the deadline for submitting the Project Conceptual Plan, as described in § 250.226:

(a) The project is similar to projects involving subsea tieback development technology for which you have obtained approval previously, and

(b) The project does not involve either new or unusual technology or a new platform.