Skip to content
LexBuild

30 CFR § 250.714 - Do I have to develop a dropped objects plan?

---
identifier: "/us/cfr/t30/s250.714"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "30 CFR § 250.714 - Do I have to develop a dropped objects plan?"
title_number: 30
title_name: "Mineral Resources"
section_number: "250.714"
section_name: "Do I have to develop a dropped objects plan?"
chapter_name: "BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "B"
subchapter_name: "OFFSHORE"
part_number: "250"
part_name: "OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334."
regulatory_source: "76 FR 64462, Oct. 18, 2011, unless otherwise noted."
cfr_part: "250"
---

# 250.714 Do I have to develop a dropped objects plan?

If you use a floating rig unit in an area with subsea infrastructure, you must develop a dropped objects plan and make it available to BSEE upon request. This plan must be updated as the infrastructure on the seafloor changes. Your plan must include:

(a) A description and plot of the path the rig will take while running and pulling the riser;

(b) A plat showing the location of any subsea wells, production equipment, pipelines, and any other identified debris;

(c) Modeling of a dropped object's path with consideration given to metocean conditions for various material forms, such as a tubular (e.g., riser or casing) and box (e.g., BOP or tree);

(d) Communications, procedures, and delegated authorities established with the production host facility to shut-in any active subsea wells, equipment, or pipelines in the event of a dropped object; and

(e) Any additional information required by the District Manager as appropriate to clarify, update, or evaluate your dropped objects plan.