30 CFR § 250.867 - Temporary quarters and temporary equipment.
---
identifier: "/us/cfr/t30/s250.867"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "30 CFR § 250.867 - Temporary quarters and temporary equipment."
title_number: 30
title_name: "Mineral Resources"
section_number: "250.867"
section_name: "Temporary quarters and temporary equipment."
chapter_name: "BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "B"
subchapter_name: "OFFSHORE"
part_number: "250"
part_name: "OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334."
regulatory_source: "76 FR 64462, Oct. 18, 2011, unless otherwise noted."
cfr_part: "250"
---
# 250.867 Temporary quarters and temporary equipment.
(a) You must equip temporary quarters with all safety devices required by API RP 14C, Appendix C (incorporated by reference as specified in § 250.198). The District Manager must approve the safety system/safety devices associated with the temporary quarters prior to installation.
(b) The District Manager may require you to install a temporary firewater system for temporary quarters in production processing areas or other classified areas.
(c) Temporary equipment associated with the production process system, including equipment used for well testing and/or well clean-up, must be approved by the District Manager.
(d) The District Manager must approve temporary generators that would require a change to the electrical one-line diagram in § 250.842(a).
[81 FR 61918, Sept. 7, 2016, as amended at 83 FR 49259, Sept. 28, 2018]