Skip to content
LexBuild

46 CFR § 162.161-9 - Procedure for approval.

---
identifier: "/us/cfr/t46/s162.161-9"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "46 CFR § 162.161-9 - Procedure for approval."
title_number: 46
title_name: "Shipping"
section_number: "162.161-9"
section_name: "Procedure for approval."
chapter_name: "COAST GUARD, DEPARTMENT OF HOMELAND SECURITY"
subchapter_number: "Q"
subchapter_name: "EQUIPMENT, CONSTRUCTION, AND MATERIALS: SPECIFICATIONS AND APPROVAL"
part_number: "162"
part_name: "ENGINEERING EQUIPMENT"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "33 U.S.C. 1321(j), 1903; 46 U.S.C. 3306, 3703, 4104, 4302; E.O. 12234, 45 FR 58801, 3 CFR, 1980 Comp., p. 277; E.O. 12777, 56 FR 54757, 3 CFR, 1991 Comp., p. 351; DHS Delegation 00170.1, Revision No. 01.4."
cfr_part: "162"
---

# 162.161-9 Procedure for approval.

(a) Preapproval review is required as detailed in 46 CFR 159.005-5 and 159.005-7.

(b) Applications for approval must be submitted in accordance with 46 CFR 159.005-9 through 159.005-12 to the Commandant (CG-5214). In addition to the listed requirements:

(1) Evidence must be shown that an acceptable follow-up factory inspection program is in place in each factory location. This could be demonstrated by providing an original copy of the contract for a follow-up program between the manufacturer and the independent laboratory. The follow-up program must include provisions that prohibit changes to the approved equipment without review and approval by the independent laboratory.

(2) Two design, installation, operation and maintenance manuals must be submitted.